VIDEO: Foothill Gold Line Project Update Highlights – June 2024

The 9.1-mile, four-station Glendora to Pomona project segment is now 88% complete. The on-budget project continues to be on schedule to reach substantial completion and turn-over to LA Metro in just six months. This past month, the project reached a major milestone when crews completed installation of the light rail power system – the final element to be completed of the new light rail system that includes the tracks, train control system and power system. Crews are now busy readying the project for train testing that’s set to commence later this month.

Additionally, earlier this month the procurement process to hire the design-build team for the 3.2-mile, two-station Pomona to Montclair project reached its next step when responses were received to the Request for Qualifications (RFQ).

Click here or below to watch the June 2024 highlight video to see these latest activities and more.